Administrative Bulletin |
|
Bulletin Number |
|
|
|
INFORMATION
RELEASE
|
|
The distribution of
Operating System Patches for all EDP platforms will now adhere to the following
rules. |
||
All
machines will be split into 3 categories. The categories are as follows:
|
Category ONE | |
Machine
types that have been supplied by EDP within the last 18 months. These
platforms will remain in this category for 18 months after the last machine
of its type was installed as new. |
|
Category TWO | |
Machine
types that have been supplied by EDP within the last 4 years. These platforms
will remain in this category for 4 years after the last machine of its
type was installed as new. |
|
Category THREE | |
All
other machines |
|
Patch
distribution rules for these machines are as follows:
|
|
Category ONE | |
New
Maintenance Editions and Interim patches will be distributed to these
platforms immediately after passing the qualification procedures. |
|
Category TWO | |
New
Maintenance Editions and Interim patches will only be distributed to these
platforms to cure problems the customer may be experiencing. The patches
may be pre-qualified on these platforms. |
|
Category THREE | |
New
Maintenance Editions and Interim patches will not be qualified or distributed
on these platforms. If a specific job or upgrade necessitates loading
a particular patch or patches on a machine in this category, the kit will
first have to pass the qualification procedures. |
|
However,
whenever possible such jobs on machines in this category should be avoided
and the customer advised to purchase a machine from category 1. |
|